Summary
Owner/Location: MRPL, Mangalore
Mode of Execution: EPC
Key Features
- Overall Capacity : 2.2 MMTPA
- Major Processing Units: PFCCU with PRU
- Total Project Cost (in USD): USD 300 million
- Schedule : 36 Months
Challenges
Procurement: Large number of drawings/documents and RFPs (247 Nos.)
Construction: Due to mountainous terrain, movement of ODC consignments was a real challenge.

PFCCU, MRPL Ph-III
Achievements
HSE: 3.85 Million Construction Man-hour achieved without Lost Time Accident