PFCCU, MRPL Ph-III

Summary

Owner/Location: MRPL, Mangalore
Mode of Execution: EPC

Key Features

  • Overall Capacity : 2.2 MMTPA
  • Major Processing Units: PFCCU with PRU
  • Total Project Cost (in USD): USD 300 million
  • Schedule : 36 Months

Challenges

Procurement: Large number of drawings/documents and RFPs (247 Nos.)

Construction: Due to mountainous terrain, movement of ODC consignments was a real challenge.

PFCCU, MRPL Ph-III

Achievements

HSE: 3.85 Million Construction Man-hour achieved without Lost Time Accident