PFCCU, MRPL Ph-III

Summary

Owner/Location: MRPL, Mangalore

Mode of Execution: EPC

Key Features
  • Overall Capacity:2.2 MMTPA
  • Major Processing Units: PFCCU with PRU
  • Total Project Cost: USD 300 million
  • Schedule: 36 Months
PFCCU, MRPL Ph-III

Challenges

Procurement: Large number of drawings/documents and RFPs (247 Nos.)

Construction: Due to mountainous terrain, movement of ODC consignments was a real challenge.

Achievements

HSE: 

3.85 Million Construction Man-hour achieved without Lost Time Accident