Panipat Naphtha Cracker

Summary

Mode of Execution: Pre FEED, FEED & PMC

Key Features

Overall Capacity : 2.2 MMTPA

  • 800 KTA Ethylene
  • 660 KTA Propylene
Major Processing Units: HGU, Pyrolysis Gasoline Hydrogenation, Benzene Extraction Unit, PPU, LLDPE/HDPE Swing Unit, HDPE, Utility Boilers, Cooling Tower, DM Plant, Effluent Treatment Plant, O2/N2 Plant, Offsite Storage and Dispatch facility
Total Project Cost: USD 2.4 billion
Schedule: 42 Months

Challenges

Process

  • Zero Effluent discharge from the complex. Designed for 100% re-use of facility.
  • Liquid effluent treatment conformed to the MINAS statutory Standards.

Panipat Naphtha Cracker

Procurement

Procurement of following items through 54 nos Indian vendors and 18 nos foreign vendors:

  • 300 nos of Equipment
  • 50 nos of Piping
  • 30 nos of Instrumentation
  • 17 nos of Electricals

Achievements

HSE: 75 million Construction Man-hour achieved without Lost Time Accident.

Cost Saving: More than Rs.300 Crores savings to client on estimated project cost after award of LSTK contract to EIL.

Awards

  • 128 days time saving w. r. t actual completion for world scale size naphtha cracker complex.
  • Project completion in 46 months is the lowest time schedule at global level.